Hallway

The two weeks since the previous construction update have been productive. As you can see from the images below, most of the framing in the office and secure entrance is completed. Additionally, duct work was removed and inspected, restrooms are roughed in and a lot of electrical conduit and wire is being pulled. The first image below is the framed out principal office that will overlook the main north/south hallway to the dome and lunch room.

Principal Office

This image is taken from the east side doors looking back to the north. The doorway you see in the picture will be the relocated office of the business manager.

East Side

This image was taken in front of the doors to the lecture hall looking north. The opening you see is to a new set of restrooms that will be publicly accessible to students during lunch and during events held in the lecture hall.

Rest Rooms

The image below shows a central hallway that runs east and west. This will be how students move from the east pod to the west pod. On the left side of the picture will be the superintendet office and teacher workroom. On the right side of the hallway is where our servers, switches and technology office is located. You can see a smaller window in the hallway on the right that students will use as a service window if they need to have something fixed with their computer.

East West Hallway

This final image is taken from the hallway to the east pod. You see the office for the media center and future location of the door on the east side of the media center.

Tech Office